Yuma Proving Grounds
Electric
General Motors
Yuma, Arizona - 2021
Battery Charging Sub-Station.
Complete the substation 4 weeks after gear arrival. The electrical equipment was delayed in manufacturing by the gear manufacturer, and the GC needed to turn the project over to GM within 6 weeks of receiving the gear.