Michigan Assembly Plant Sub Station Addition

Project

Michigan Assembly Plant Sub Station Addition

Categories

Electrical, Automotive, Industrial

Client

Ford Motor Company

Location

Wayne MI - 2019

Description

Double-ended 13KvA substation to supply power for building addition and product launch.

Challenge

Cost and speed to reduce project schedule.

Solution

  • Designed and engineered a modular substation for off-site construction in parallel with on-site activities.
  • Equipment was factory commissioned to reduce on-site timing.